1- Taking the land to “SELEM LAND POOL” by carrying out R&D studies.
2- Purchase of the land from the Land Pool by the Participating Member
3- Giving a power of attorney to the Vakar Architecture Office staff(s) of the Participant Member from the Notary in order to be able to carry out transactions with the land.
4- Obtaining the Zoning Diameter from the relevant Municipality
5- Making the project design according to the requests of the Zoning Area and the Participating Member.
6- The Participant Member and the Architect together choose the materials to be used in the project.
7- Preliminary Project of the Project is prepared.
8- The "Initial Approximate Cost Calculation" of the project is prepared.
9- The Participant Member's payment plan is made according to the Project's Initial Approximate Cost Calculation.
10- Implementation project is prepared according to the pre-prepared project.
11- A "BUILDING LICENSE" is obtained from the relevant Municipality Zoning Directorate.
12- A production plan is made for the construction of the project, for which the building permit has been obtained.
13- Selected material supplies and connections are made.
14- Work is delivered to the “Business Partner” firm(s) from the Production Group, starting with the Rough Works.
15- At the end of each month, the construction site staff arranges progress payments related to the work done by the field workers.
16- The company staff responsible for the construction site starts each team according to the workflow, according to the work order.
17- Responsible construction site personnel receives their delivered works completely and completely.
18- When the work done is completed, “Work Completion Certificates” are received from the competent authorities.
19- When the construction process is completed, an application is made to the municipality for the necessary documents for the " BUILDING USE PERMISSION - SETTLEMENT CERTIFICATE ".
20- With the completion of the process by the person responsible for the follow-up, the works and procedures that the Company has to do regarding the Construction are completed.
21- “FINAL COST ACCOUNT” of the Participant Member is issued. Account reconciliation is done. If the participant member has debts, it is closed.
22- "TURN-KEY" is made to the Participating Member.
23- The Participant Member can purchase his/her home by purchasing subscribers such as Electricity, Water, Natural Gas.